10 free, exam-style Certified Grants Management Specialist (CGMS) practice questions with answers and
explanations. No signup required. Work through them below, then take the
full free CGMS practice test to study every exam domain.
These 10 free CGMS questions are organized by exam domain, so you can see how each part of the Certified Grants Management Specialist blueprint is tested. Reveal the answer and explanation under each question.
Domain 1: Grant Guidance 23% of exam
Question 1
A federal agency plans to fund a community health initiative and expects to be actively involved in programmatic decision-making throughout the project. The MOST appropriate funding instrument for this arrangement is a:
- Cooperative agreement
- Discretionary grant
- Procurement contract
- Block grant
Show answer & explanation
Correct answer: A - Cooperative agreement
Question 2
A subrecipient's internal travel policy allows a higher per diem rate than the rate established in the federal award terms and conditions. When charging travel costs to the federal award, the subrecipient must follow:
- Its own internal travel policy, since organizational policies govern employee travel
- The more restrictive of the two rates
- The federal per diem rate published by the General Services Administration
- Whichever rate the pass-through entity approves in writing
Show answer & explanation
Correct answer: B - The more restrictive of the two rates
Domain 2: Grant Award 29% of exam
Question 3
A state agency receives a federal education grant and engages a local nonprofit to recruit eligible families and deliver tutoring services to students in underserved communities. The nonprofit has discretion in selecting participants and determining service delivery methods. Under 2 CFR Part 200, the nonprofit is MOST appropriately classified as a:
- Subrecipient
- Contractor
- Vendor
- Consultant
Show answer & explanation
Correct answer: A - Subrecipient
Question 4
When issuing a subaward, a pass-through entity discovers the subrecipient has never received federal funding, has recently hired a new finance director, and had a qualified opinion on its most recent financial audit. Under 2 CFR Part 200, the pass-through entity's FIRST action should be to:
- Deny the subaward until the subrecipient resolves its audit findings
- Issue the subaward with standard terms and a routine monitoring schedule
- Evaluate the subrecipient's risk of noncompliance and adjust monitoring accordingly
- Require the subrecipient to obtain a single audit before the subaward is executed
Show answer & explanation
Correct answer: C - Evaluate the subrecipient's risk of noncompliance and adjust monitoring accordingly
Question 5
A pass-through entity receives a subrecipient's single audit report containing findings related to the federal award. Under 2 CFR Part 200, the pass-through entity must issue a management decision on those findings within:
- 30 days of receiving the audit report
- 6 months of the end of the audit period
- 9 months of the subrecipient's fiscal year end
- 12 months of receiving the audit report
Show answer & explanation
Correct answer: D - 12 months of receiving the audit report
Domain 3: Fiscal Management 25% of exam
Question 6
A grant-funded program coordinator purchases a $45 bottle of wine to serve at a working dinner with community partners to discuss project outcomes. The coordinator argues the dinner had a clear programmatic purpose. Under 2 CFR Part 200, this cost is:
- Unallowable, because alcoholic beverages are prohibited regardless of purpose
- Allowable, because the dinner served a programmatic purpose
- Allowable if pre-approved by the federal awarding agency
- Allowable if documented and within the approved budget for meetings
Show answer & explanation
Correct answer: A - Unallowable, because alcoholic beverages are prohibited regardless of purpose
Question 7
A small nonprofit receiving its first federal award has never negotiated an indirect cost rate with a federal agency. Under the current Uniform Guidance, the organization may elect to charge indirect costs at:
- 10% of modified total direct costs
- 15% of total direct costs
- 15% of modified total direct costs
- A rate determined by the nonprofit's board of directors
Show answer & explanation
Correct answer: C - 15% of modified total direct costs
Question 8
A nonprofit's federal grant has the following direct costs: $200,000 in salaries and fringe benefits, $30,000 in travel, $18,000 in equipment, $20,000 in participant support costs, and an $80,000 subaward. Using the de minimis rate of 15% of MTDC, the allowable indirect cost recovery is:
- $52,200
- $28,000
- $42,000
- $34,500
Show answer & explanation
Correct answer: C - $42,000
Domain 4: Program Management 22% of exam
Question 9
At the end of a federal award, a recipient has a piece of equipment originally purchased with grant funds for $50,000. The equipment has a current fair market value of $8,000. Under 2 CFR Part 200, the recipient:
- Must return the equipment to the federal awarding agency for disposition
- Must compensate the federal government for its proportional share of the $8,000
- Must transfer the equipment to another active federal grant within the organization
- May retain, sell, or dispose of it with no further obligation
Show answer & explanation
Correct answer: D - May retain, sell, or dispose of it with no further obligation
Question 10
A federally funded job training program reports that 300 participants completed the 12-week course during the first year. In a logic model framework, this figure represents a(n):
- Outcome
- Output
- Impact
- Activity
Show answer & explanation
Correct answer: B - Output